This test is designed to help you prepare for the actual CCM exam by covering a wide range of topics that are essential for construction management professionals.
The test consists of 50 multiple-choice questions that will assess your knowledge.
The test includes areas such as project management, cost control, scheduling, safety, contracts, and more.
Use this practice test to identify your strengths and areas where you may need further study.
Popular Programs
Featured Online Programs
Learn at home, at your own pace.
Electrician
Request InfoHVAC Tech
Request InfoAuto Mechanic
Request InfoPhlebotomy Technician
Request InfoMedical Assistant
Request InfoMedical Billing and Coding
Request InfoSee More Trades
Request InfoGood luck!
Certified Construction Manager (CCM) Practice Test
Congratulations - you have completed Certified Construction Manager (CCM) Practice Test.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
What is the primary purpose of a project charter in construction management?
To define the project scope | |
To authorize the project | |
To outline the budget | |
To identify stakeholders |
Question 2 |
Which of the following is a key component of a Work Breakdown Structure (WBS)?
Resource allocation | |
Task dependencies | |
Hierarchical decomposition | |
Risk assessment |
Question 3 |
What is the critical path in a project schedule?
The longest path through the project with zero float | |
The shortest path through the project | |
The path with the most resources | |
The path with the highest risk |
Question 4 |
Which contract type places the most risk on the contractor?
Cost-plus-fee | |
Lump sum | |
Time and materials | |
Unit price |
Question 5 |
What is the main purpose of a risk management plan?
To eliminate all project risks | |
To identify, assess, and mitigate risks | |
To transfer all risks to the owner | |
To ignore minor risks |
Question 6 |
Which of the following is NOT a typical phase in the construction project lifecycle?
Initiation | |
Design | |
Execution | |
Marketing |
Question 7 |
What is the primary goal of value engineering in construction?
To reduce project costs without sacrificing quality | |
To increase the project scope | |
To extend the project schedule | |
To maximize the use of premium materials |
Question 8 |
Which document is used to formally request changes to the project scope?
Change order | |
Request for Information (RFI) | |
Submittal | |
Punch list |
Question 9 |
What is the purpose of a preconstruction meeting?
To finalize the project budget | |
To review project plans and clarify roles | |
To award the contract | |
To close out the project |
Question 10 |
Which of the following is a key responsibility of a construction manager during the construction phase?
Designing the project | |
Ensuring compliance with safety regulations | |
Marketing the project | |
Securing financing |
Question 11 |
What is the primary purpose of a construction schedule?
To track project costs | |
To sequence and coordinate project activities | |
To identify project risks | |
To document change orders |
Question 12 |
Which of the following is a common method for resolving construction disputes?
Mediation | |
Litigation | |
Arbitration | |
All of the above |
Question 13 |
What is the main purpose of a punch list?
To identify incomplete or defective work | |
To track project expenses | |
To document safety violations | |
To schedule subcontractors |
Question 14 |
Which of the following is a key element of a construction safety program?
Regular safety training | |
Minimizing the use of personal protective equipment (PPE) | |
Ignoring minor safety violations | |
Reducing the number of safety inspections |
Question 15 |
What is the primary purpose of a construction budget?
To estimate the total cost of the project | |
To track project progress | |
To identify project risks | |
To document change orders |
Question 16 |
Which of the following is a key factor in selecting a construction delivery method?
Project complexity | |
Owner’s risk tolerance | |
Project schedule | |
All of the above |
Question 17 |
What is the primary purpose of a construction contract?
To define the roles and responsibilities of all parties | |
To outline the project schedule | |
To identify project risks | |
To document change orders |
Question 18 |
Which of the following is a key component of a quality management plan?
Quality assurance | |
Quality control | |
Continuous improvement | |
All of the above |
Question 19 |
What is the primary purpose of a construction submittal?
To request payment | |
To document compliance with contract documents | |
To identify project risks | |
To schedule subcontractors |
Question 20 |
Which of the following is a key responsibility of a construction manager during the closeout phase?
Finalizing the project budget | |
Ensuring all project deliverables are completed | |
Marketing the project | |
Securing financing |
Question 21 |
What is the primary purpose of a construction risk assessment?
To identify potential risks and their impacts | |
To eliminate all project risks | |
To transfer all risks to the owner | |
To ignore minor risks |
Question 22 |
Which of the following is a key factor in successful project communication?
Regular meetings | |
Clear documentation | |
Effective stakeholder engagement | |
All of the above |
Question 23 |
What is the primary purpose of a construction contingency plan?
To address unforeseen events that may impact the project | |
To reduce project costs | |
To extend the project schedule | |
To maximize the use of premium materials |
Question 24 |
Which of the following is a key component of a construction project’s scope statement?
Project objectives | |
Deliverables | |
Constraints | |
All of the above |
Question 25 |
What is the primary purpose of a construction progress report?
To track project progress and identify issues | |
To document change orders | |
To identify project risks | |
To schedule subcontractors |
Question 26 |
Which of the following is a key responsibility of a construction manager during the design phase?
Reviewing design documents for constructability | |
Managing construction activities | |
Marketing the project | |
Securing financing |
Question 27 |
What is the primary purpose of a construction procurement plan?
To identify and acquire necessary resources | |
To track project progress | |
To identify project risks | |
To document change orders |
Question 28 |
Which of the following is a key factor in successful project cost control?
Accurate cost estimating | |
Regular budget reviews | |
Effective change management | |
All of the above |
Question 29 |
What is the primary purpose of a construction safety inspection?
To identify and mitigate safety hazards | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 30 |
Which of the following is a key component of a construction project’s communication plan?
Stakeholder analysis | |
Communication methods | |
Frequency of communication | |
All of the above |
Question 31 |
What is the primary purpose of a construction project’s risk register?
To document identified risks and their mitigation strategies | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 32 |
Which of the following is a key responsibility of a construction manager during the procurement phase?
Managing subcontractor bids | |
Reviewing design documents | |
Marketing the project | |
Securing financing |
Question 33 |
What is the primary purpose of a construction project’s quality control plan?
To ensure that work meets specified standards | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 34 |
Which of the following is a key factor in successful project scheduling?
Accurate task duration estimates | |
Effective resource allocation | |
Regular schedule updates | |
All of the above |
Question 35 |
What is the primary purpose of a construction project’s change management plan?
To manage changes to the project scope, schedule, and budget | |
To track project progress | |
To document safety violations | |
To schedule subcontractors |
Question 36 |
Which of the following is a key responsibility of a construction manager during the initiation phase?
Developing the project charter | |
Managing construction activities | |
Marketing the project | |
Securing financing |
Question 37 |
What is the primary purpose of a construction project’s stakeholder management plan?
To identify and engage stakeholders | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 38 |
Which of the following is a key component of a construction project’s cost management plan?
Cost estimating | |
Budgeting | |
Cost control | |
All of the above |
Question 39 |
What is the primary purpose of a construction project’s procurement management plan?
To identify and acquire necessary resources | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 40 |
Which of the following is a key responsibility of a construction manager during the execution phase?
Overseeing construction activities | |
Reviewing design documents | |
Marketing the project | |
Securing financing |
Question 41 |
What is the primary purpose of a construction project’s risk management plan?
To identify, assess, and mitigate risks | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 42 |
Which of the following is a key factor in successful project quality management?
Quality planning | |
Quality assurance | |
Quality control | |
All of the above |
Question 43 |
What is the primary purpose of a construction project’s communication management plan?
To ensure effective communication among stakeholders | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 44 |
Which of the following is a key responsibility of a construction manager during the monitoring and controlling phase?
Tracking project progress and performance | |
Reviewing design documents | |
Marketing the project | |
Securing financing |
Question 45 |
What is the primary purpose of a construction project’s scope management plan?
To define and control the project scope | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 46 |
Which of the following is a key component of a construction project’s time management plan?
Schedule development | |
Schedule control | |
Task sequencing | |
All of the above |
Question 47 |
What is the primary purpose of a construction project’s human resource management plan?
To identify and manage project team members | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 48 |
Which of the following is a key responsibility of a construction manager during the planning phase?
Developing the project management plan | |
Managing construction activities | |
Marketing the project | |
Securing financing |
Question 49 |
What is the primary purpose of a construction project’s integration management plan?
To coordinate all project activities and processes | |
To track project progress | |
To document change orders | |
To schedule subcontractors |
Question 50 |
Which of the following is a key factor in successful project stakeholder management?
Identifying stakeholders | |
Understanding stakeholder needs | |
Engaging stakeholders throughout the project | |
All of the above |
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
There are 50 questions to complete.